SemiconductorsBRIEF

TSMC Says JASM Kumamoto Fabs Confirmed Safe After Quake, Equipment Recalibration Still Underway

林紀旭 James LinEditor-in-Chief
Published · Updated
According to a TechNews report citing TSMC's July 30 statement, JASM's Kumamoto plant had no injuries or structural damage after the July 28 magnitude-7 earthquake, but production equipment still needs recalibration. CNA separately reported the quake registered magnitude 7.1 with maximum intensity 7, while TSMC said onsite intensity reached 5 and construction resumed July 29.

How Strong Was the Kumamoto Earthquake?

According to TSMC's own statement, as reported by TechNews, Japan's Kumamoto region "experienced a magnitude-7 earthquake on July 28, followed by multiple aftershocks of considerable magnitude." A separate report from CNA, citing Japanese authorities, gave more precise figures: the quake struck Kumamoto Prefecture at 4:27 p.m. local time on July 28 with a magnitude of 7.1, a maximum seismic intensity of 7, and a focal depth of 10 kilometers.

The two figures — TSMC's "magnitude 7" and CNA's "magnitude 7.1" — describe the same event but differ slightly in the reported number, illustrating how a company statement and a wire report can present the same earthquake with different precision.

Are JASM Staff and Facilities Safe?

TechNews reported that TSMC's JASM wafer fab in Kumamoto recorded a maximum seismic intensity of 5 at the site itself — lower than the 7 reported region-wide by CNA. Per TSMC's statement, JASM "activated internal safety procedures immediately when the earthquake struck and evacuated personnel right away; all evacuated staff were confirmed safe."

By July 30, TSMC said it had "completed a post-earthquake damage inspection of the JASM plant building and confirmed the structure is safe," according to TechNews.

What Is the Status of Plant Systems and Equipment Calibration?

TSMC's July 30 statement, reported by TechNews, said JASM's "water supply, electricity, and industrial safety systems are operating normally, and inspection and calibration work related to production equipment is ongoing." CNA, reporting a day earlier on July 29, quoted TSMC saying that "because the shaking was relatively large this time, the Kumamoto JASM wafer fab is expected to need some time to adjust and calibrate." Together, the two reports show recalibration work spanning at least from July 29 through July 30, with no completion date given in either.

How Is TSMC Supporting JASM's Recovery?

According to TechNews, TSMC said that "after taking stock, TSMC has also deployed resources to support JASM, and raw material supply is currently not a concern." No further detail on the scale or nature of the resources was provided in the statement.

Where Does Construction and Capacity Stand?

TechNews reported that JASM's construction site "was not affected, and after confirming safety, construction resumed yesterday (the 29th)" — referring to July 29, one day after the earthquake. This sits alongside the fab's broader production timeline reported by CNA: JASM's first wafer fab entered volume production at the end of 2024 using a specialty process technology, while a second Kumamoto fab is planned to use 3-nanometer process technology, with mass production targeted for 2028.

Date / MilestoneDetailSource
Jul 28, 2026Earthquake: M7 (TSMC) / M7.1, max intensity 7, depth 10km (CNA)TechNews / CNA
Jul 28, 2026JASM site max intensity: 5TechNews
Jul 29, 2026JASM construction site resumes work after safety checkTechNews
Jul 30, 2026TSMC confirms building structure safe, systems normal, calibration ongoingTechNews
End of 2024JASM Fab 1 enters volume production (specialty process)CNA
2028 (planned)JASM Fab 2 targets mass production on 3nm processCNA

Is TSMC Reviewing Impact and Talking to Customers?

TSMC said, as quoted by TechNews, "we are conducting a comprehensive review of the impact caused by this earthquake, and are maintaining close communication with customers." No specifics on customer commitments or review findings were disclosed in the statement.

What This Means

Reading the two reports together shows a fab that came through a major regional earthquake — magnitude 7 to 7.1 depending on the source — with confirmed personnel safety and structural integrity, but with production equipment calibration still an open item as of TSMC's July 30 statement, a day after CNA first reported the quake would require "some time" to adjust for. Construction on the second, 3nm-targeted fab resumed within a day (July 29), while TSMC's language on resource deployment, raw material supply, and customer communication stops short of specifying a timeline for when calibration — and any related output impact — will be complete.

📊 Evidence

FAQ

Was anyone injured at JASM during the earthquake?

No. TSMC said JASM evacuated personnel immediately under its internal safety procedures, and all evacuated staff were confirmed safe, according to TechNews.

Has construction resumed at JASM's second Kumamoto fab?

Yes. TechNews reported the construction site was unaffected by the quake and work resumed on July 29 after safety was confirmed.

When is JASM's second Kumamoto fab expected to start mass production?

CNA reported the second fab will use 3-nanometer process technology and is targeted for mass production in 2028.

📎 Sources

  1. technews.tw
  2. cna.com.tw
林紀旭 James LinEditor-in-Chief

Related

BRIEF

Microsoft's Single-Day Market Cap Gain Tops Nvidia's Record, Adding Nearly $450 Billion

According to Technews, Microsoft's stock surged more than 15% on July 31, lifting its market capitalization to $3.35 trillion (NT$107.8 trillion) and adding nearly $450 billion in a single day — a gain that overtakes Nvidia's prior record of $441 billion set in April last year, as strong cloud and AI results drove the rally.

林紀旭 James Lin ·
BRIEF

ASE Technology Spends Nearly NT$12 Billion to Acquire Kuai Kuai and AUO Plants as It Expands LEAP Advanced Packaging Capacity

According to CNA and UDN, ASE Semiconductor (日月光半導體) on July 30, 2026 agreed to buy land and buildings from snack maker Kuai Kuai (乖乖) for roughly NT$5.672–5.673 billion and a plant from AUO (友達) for NT$6.3 billion, a combined NT$11.973 billion. Parent ASE Investment Holdings (日月光投控) is separately raising 2026 capital spending toward an analyst-estimated US$10.5 billion to expand LEAP advanced packaging output.

林紀旭 James Lin ·